[1]赵立财.长大隧道陡坡斜井设计优化对施工进度影响研究[J].应用科技,2018,45(04):124-130,136.[doi:10.11991/yykj.201702005]
 ZHAO Licai.Study on the construction progress affected by the long tunnel steep slope inclined shaft design optimization[J].Applied science and technology,2018,45(04):124-130,136.[doi:10.11991/yykj.201702005]
点击复制

长大隧道陡坡斜井设计优化对施工进度影响研究(/HTML)
分享到:

《应用科技》[ISSN:1009-671X/CN:23-1191/U]

卷:
第45卷
期数:
2018年04期
页码:
124-130,136
栏目:
建筑工程
出版日期:
2018-08-05

文章信息/Info

Title:
Study on the construction progress affected by the long tunnel steep slope inclined shaft design optimization
作者:
赵立财
天津大学 水利工程仿真与安全国家重点实验室, 天津 300354
Author(s):
ZHAO Licai
State Key Laboratory of Hydraulic Engineering Simulation and Safety, Tianjin University, Tianjin 300354, China
关键词:
斜井结构陡坡纵坡优化设计进度成本工期
Keywords:
inclined shaftstructuresteep slopelongitudinal slopeoptimal designprogresscostconstruction period
分类号:
U45
DOI:
10.11991/yykj.201702005
文献标志码:
A
摘要:
结合斜井所处地段地质状况,从工期分析、安全分析、成本分析3个方面对原设计斜井方案进行了优化前后比较并提出了3种优化方案。通过纵向坡度调整、洞口位置、设计方案等因素分析,确定选用优化方案1组织斜井施工,以加快施工进度,以保证整条隧道的工期目标实现。优化方案1将IV、V级围岩优化为Ⅲ级围岩,钢纤维喷射混凝土取代钢架和二次衬砌结构,可节省小断面陡坡长斜井支护及开挖的施工时间,优化后斜井比原方案节省工期189 d。有效解决了出渣、材料运输问题,妥善处理了弃碴、安全、拟投入的人员、机械设备、材料与工程规模等多方面问题,可为今后类似工程施工提供经验。
Abstract:
According to the geological condition of the inclined shaft location, this paper makes a comparative analysis of the inclined shaft design scheme before and after optimization from three aspects:construction period, safety and cost. Through factor analysis, including longitudinal slope adjustment, entrance position, design scheme, etc., the optimal scheme is determined, and then organize the construction so as to speed up the construction progress and ensure the construction period of the entire tunnel project. The first optimal scheme optimizes grade IV and grade V surrounding rock into grade Ⅲ surrounding rock, substitutes steel fiber shotcrete for steel frame and the secondary lining structure, which can save the construction period of the support and excavation project of the small section long inclined shaft. The optimized scheme has shortened 189 days of construction period than former scheme. The scheme has solved the problem of deslagging and material transportation effectively, properly dealt with the problems of waste rock, safety, personnel to be arranged, mechanical device, materials, project scale and so on, providing experience for similar projects in the future.

参考文献/References:

[1] 李志平, 李永生. 关角隧道单车道无轨斜井施工方案优化[J]. 隧道建设, 2010, 30(1):53-57.
[2] 蔡振宇, 陈海波, 李志平. 西汉高速公路秦岭Ⅰ号隧道通风斜井方案优化[J]. 隧道建设, 2008, 28(2):201-204.
[3] 刘锁. 鄂赣特长公路隧道陡坡通风斜井设计方案优化与施工[J]. 隧道建设, 2014, 34(10):959-966.
[4] 邢利华. 新建兰渝铁路后山坪隧道斜井施工方案优化[J]. 浙江建筑, 2015, 35(6):38-40, 49.
[5] 李猛. 兴旺峁隧道3#斜井优化方案[J]. 科技传播, 2011(7):123-124.
[6] 周本敏. 长大隧道快速施工的技术方案及经济评估研究[D]. 天津:天津大学, 2006.
[7] 王继波. 铁法晓南煤矿二水平延深设计方案优化研究[D]. 阜新:辽宁工程技术大学, 2005.
[8] 李鸿博, 申思然. 公路隧道陡坡斜井纵坡优化设计[J]. 公路交通科技:应用技术版, 2013, 9(7):181-184.
[9] 柳果红, 胡铁锋. 大相岭隧道通风斜井施工方案优化[J]. 广东公路交通, 2017, 43(3):42-46.
[10] 吴同勋. 王家沟煤矿下组煤层延深开采开拓方案优化[J]. 能源与节能, 2015(12):153-154.
[11] 张俊兴. 长大铁路隧道快速施工技术剖析[J]. 铁道建筑技术, 2016(S1):252-254, 343.
[12] 刘磊. 长距离斜井快速施工技术研究及应用[J]. 山东煤炭科技, 2015(5):51-52.

备注/Memo

备注/Memo:
收稿日期:2017-2-26。
作者简介:赵立财(1985-),男,高级工程师.
通讯作者:赵立财,E-mail:zhaolicai@tju.edu.cn